Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most lik
Posted in Category : 
Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days,
and a pessimistic time estimate of 10 days. Its expected time is approximately: Answer 8 6 7 9 5